PJM-AH2-217
100 MW storage in Morrow, OH · In queue since March 2022 · Proposed COD December 2026
100 MW
Capacity
1
Components
Battery
4y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Total Duration
4y 9m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-12-31
PJM-AH2-217 is a proposed 100 MW battery storage project located in Morrow County, Ohio. The project is interconnected to the ATSI utility network and participates in the PJM Interconnection queue. The queue entry date is March 9, 2022, with a proposed commercial operation date of December 31, 2026.
The project's interconnection agreement status is listed as "In Progress (unknown study)".
Generated from interconnection queue and public data sources
State
OH
County
Morrow
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
ATSI
Entity
PJM
Service Type
—
Point of Interconnection
Cardington 138 kV II
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AH2-217