PJM-AH2-242
45 MW hybrid in Montgomery, OH · In queue since March 2022 · Proposed COD March 2027
45 MW
Capacity
1
Components
Solar
4y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2027
Total Duration
5 years
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-03-08
PJM-AH2-242 is a proposed 45 MW hybrid solar and battery project located in Montgomery County, Ohio. The project, which consists of 45 MW of solar generation, is in the PJM interconnection queue as of March 9, 2022, with a proposed commercial operation date of March 8, 2027. The point of interconnection is the Crown - New Lebanon 69 kV substation, and the interconnecting utility is Dayton.
The interconnection agreement for PJM-AH2-242 is currently listed as "In Progress (unknown study)".
Generated from interconnection queue and public data sources
State
OH
County
Montgomery
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
Dayton
Entity
PJM
Service Type
—
Point of Interconnection
Crown - New Lebanon 69 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AH2-242