PJM-AH2-244
25 MW storage in Allegheny, PA · In queue since March 2022 · Proposed COD September 2023
25 MW
Capacity
1
Components
Battery
4y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2023
Total Duration
1y 6m
Schedule
32 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-09-29
PJM-AH2-244 is a proposed 25 MW battery storage project located in Allegheny County, Pennsylvania. The project, which consists solely of battery storage, is interconnected within the PJM Interconnection queue. Its queue entry date is March 9, 2022, with a proposed commercial operation date of September 29, 2023. The interconnection agreement status is currently listed as "In Progress (unknown study)".
The proposed project is located within the Duquesne Light (DL) service territory. The point of interconnection (POI) is the Swickley - Ambridge 23 kV line. The project is currently listed as active within the PJM queue.
Generated from interconnection queue and public data sources
State
PA
County
Allegheny
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
DL
Entity
PJM
Service Type
—
Point of Interconnection
Swickley - Ambridge 23 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.