PJM-AH2-253
70 MW hybrid in Beaver, PA · In queue since March 2022 · Proposed COD November 2025
70 MW
Capacity
1
Components
Solar
4y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Total Duration
3y 8m
Schedule
5 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-11-25
The proposed project PJM-AH2-253 is a 70 MW solar and battery hybrid development located in Beaver County, Pennsylvania. Interconnecting within the PJM Interconnection queue, the project entered the queue on March 10, 2022, and has a proposed commercial operation date of November 25, 2025. The point of interconnection is the Beaver Valley - Crescent 138 kV substation.
The interconnection agreement for the project is currently listed as "In Progress (unknown study)". The project consists of 70 MW of solar generation capacity coupled with battery storage.
Generated from interconnection queue and public data sources
State
PA
County
Beaver
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
DL
Entity
PJM
Service Type
—
Point of Interconnection
Beaver Valley - Crescent 138 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- VALLEY4 230 KV SR_1
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AH2-253