PJM-AH2-258
172 MW hybrid in Kendall, IL · In queue since March 2022 · Proposed COD September 2024
172 MW
Capacity
1
Components
Solar
4y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Total Duration
2y 6m
Schedule
19 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-09-27
PJM-AH2-258 is a proposed 172 MW hybrid solar and battery project located in Kendall County, Illinois. The project consists of 172 MW of solar generation. It is interconnected within the PJM Interconnection queue, with an entry date of March 9, 2022, and a proposed commercial operation date of September 27, 2024. The interconnecting utility is ComEd, and the point of interconnection is the Plano 345 kV substation.
The project's interconnection agreement status is listed as "In Progress (unknown study)".
Generated from interconnection queue and public data sources
State
IL
County
Kendall
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
ComEd
Entity
PJM
Service Type
—
Point of Interconnection
Plano 345 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- N ILLINOIS HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- 167 PLANO
- POI Substation
- Plano Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.