PJM-AH2-259
172 MW storage in Kendall, IL · In queue since March 2022 · Proposed COD September 2024
172 MW
Capacity
1
Components
Battery
4y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Total Duration
2y 6m
Schedule
19 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-09-27
PJM-AH2-259 is a proposed battery storage project with a total capacity of 172 MW. The project is located in Kendall County, Illinois, within the ComEd service area and the PJM Interconnection region. The project entered the PJM queue on March 9, 2022, with a proposed commercial operation date of September 27, 2024.
The interconnection agreement for the project is currently listed as "In Progress (unknown study)". The point of interconnection is the Plano 345 kV substation.
Generated from interconnection queue and public data sources
State
IL
County
Kendall
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
ComEd
Entity
PJM
Service Type
—
Point of Interconnection
Plano 345 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- N ILLINOIS HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- 167 PLANO
- POI Substation
- Plano Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AH2-259