PJM-AH2-267
100 MW hybrid in Clearfield, PA · In queue since March 2022 · Proposed COD July 2025
100 MW
Capacity
1
Components
Solar
4y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Total Duration
3y 4m
Schedule
10 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-07-01
PJM-AH2-267 is a proposed 100 MW hybrid Solar+Battery project located in Clearfield County, Pennsylvania. The project consists of 100 MW of solar generation capacity. It is interconnected within the PJM Interconnection queue as of March 9, 2022, with a proposed commercial operation date of July 1, 2025. The interconnection agreement status is currently listed as "In Progress (unknown study)".
The proposed project is connected to the PENELEC utility grid at the Modera - BioEnergy Tap 115 kV point of interconnection.
Generated from interconnection queue and public data sources
State
PA
County
Clearfield
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
PENELEC
Entity
PJM
Service Type
—
Point of Interconnection
Modera - BioEnergy Tap 115 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AH2-267