PJM-AH2-269A
45 MW generation in Prince George's, MD · In queue since March 2022 · Proposed COD November 2026
45 MW
Capacity
1
Components
Gas
4y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Total Duration
4y 8m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-11-02
PJM-AH2-269A is a proposed 45 MW natural gas generation project located in Prince George's County, Maryland. The project is interconnected within the PJM Interconnection queue, with an entry date of March 10, 2022. The proposed commercial operation date is November 2, 2026.
The interconnection agreement (IA) status for the project is listed as "In Progress (unknown study)". The point of interconnection (POI) is the Burches Hill-Chalk Point 500kV substation. The project is within the PEPCO utility service area.
Generated from interconnection queue and public data sources
State
MD
County
Prince George's
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
PEPCO
Entity
PJM
Service Type
—
Point of Interconnection
Burches Hill-Chalk Point 500kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AH2-269A