PJM-AH2-270
300 MW generation in Whiteside, IL · In queue since March 2022 · Proposed COD December 2026
300 MW
Capacity
1
Components
Wind
4y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Total Duration
4y 9m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-12-31
PJM-AH2-270 is a proposed 300 MW wind generation project located in Whiteside County, Illinois. The project, which consists of 300 MW of wind capacity, is interconnected within the PJM Interconnection region via the ComEd utility. It entered the PJM queue on March 10, 2022, with a proposed commercial operation date of December 31, 2026. Its interconnection agreement status is currently listed as "In Progress (unknown study)".
The development project is located at the Point of Interconnection (POI) Garden Plain 138 kV. The project is listed as "active" within the interconnection queue.
Generated from interconnection queue and public data sources
State
IL
County
Whiteside
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
ComEd
Entity
PJM
Service Type
—
Point of Interconnection
Garden Plain 138 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- N ILLINOIS HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AH2-270