PJM-AH2-292
76.95 MW generation in Cambria, PA · In queue since March 2022 · Proposed COD December 2025
76.95 MW
Capacity
1
Components
Wind
4y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Total Duration
3y 9m
Schedule
4 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-12-31
PJM-AH2-292 is a proposed wind generation project with a total capacity of 76.95 MW. The project is located in Cambria County, Pennsylvania, within the PJM Interconnection region. The queue entry date is March 10, 2022, with a proposed commercial operation date of December 31, 2025.
The project is currently active in the PJM interconnection queue, and the Interconnection Agreement (IA) status is listed as "In Progress (unknown study)". The proposed point of interconnection (POI) is the Bear Rock 230 kV substation, and the interconnecting utility is PENELEC.
Generated from interconnection queue and public data sources
State
PA
County
Cambria
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
PENELEC
Entity
PJM
Service Type
—
Point of Interconnection
Bear Rock 230 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AH2-292