PJM-AH2-320
10 MW generation in Cambria, PA · In queue since March 2022 · Proposed COD March 2024
10 MW
Capacity
1
Components
Solar
4y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Total Duration
2 years
Schedule
26 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-03-29
PJM-AH2-320 is a proposed solar generation project located in Cambria County, Pennsylvania, within the PJM Interconnection region. The project, with a total capacity of 10 MW, consists entirely of solar photovoltaic generation. Its point of interconnection is the Revloc 34.5 kV substation.
The project entered the PJM interconnection queue on March 10, 2022, with a proposed commercial operation date of March 29, 2024. The interconnection agreement status is currently listed as "In Progress (unknown study)". The interconnecting utility is PENELEC.
Generated from interconnection queue and public data sources
State
PA
County
Cambria
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
PENELEC
Entity
PJM
Service Type
—
Point of Interconnection
Revloc 34.5 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AH2-320