PJM-AH2-334
300 MW storage in Camden, NJ · In queue since March 2022 · Proposed COD December 2025
300 MW
Capacity
1
Components
Battery
4y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Total Duration
3y 9m
Schedule
4 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-12-31
PJM-AH2-334 is a proposed 300 MW battery storage project located in Camden County, New Jersey. The project is in the PJM interconnection queue as of March 10, 2022, with a proposed commercial operation date of December 31, 2025. The interconnecting utility is PSEG. Its interconnection agreement status is listed as "In Progress (unknown study)".
The development project consists entirely of battery storage, with a total capacity of 300 MW.
Generated from interconnection queue and public data sources
State
NJ
County
Camden
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
PSEG
Entity
PJM
Service Type
—
Point of Interconnection
New Freedom 230 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- TANSBORO69 KV TANSBFC
- POI Substation
- New Freedom Switching Station
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AH2-334