PJM-AH2-338
160 MW generation in Winnebago, IL · In queue since March 2022 · Proposed COD July 2027
160 MW
Capacity
1
Components
Solar
4y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2027
Total Duration
5y 4m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-07-30
PJM-AH2-338 is a proposed 160 MW solar generation project located in Winnebago County, Illinois. The project is interconnected within the PJM Interconnection queue, having entered the queue on March 10, 2022. The proposed commercial operation date is July 30, 2027.
The interconnection agreement for PJM-AH2-338 is currently listed as "In Progress (unknown study)". The project is located within the ComEd utility service territory and will interconnect at the Wempletown 138 kV point of interconnection.
Generated from interconnection queue and public data sources
State
IL
County
Winnebago
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
ComEd
Entity
PJM
Service Type
—
Point of Interconnection
Wempletown 138 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- N ILLINOIS HUB
- Hub Confidence
- HIGH
- POI Substation
- Wempletown Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AH2-338