PJM-AH2-340
350 MW generation in Stark, IL · In queue since March 2022 · Proposed COD July 2027
350 MW
Capacity
1
Components
Solar
4y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2027
Total Duration
5y 4m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-07-30
PJM-AH2-340 is a proposed solar generation project with a total capacity of 350 MW. The project is located in Stark County, Illinois, within the ComEd service area and the PJM Interconnection region. The project entered the PJM queue on March 10, 2022, and has a proposed commercial operation date of July 30, 2027.
The interconnection agreement for PJM-AH2-340 is currently in progress, with the specific study type unknown. The point of interconnection is the Toulon 138kV substation.
Generated from interconnection queue and public data sources
State
IL
County
Stark
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
ComEd
Entity
PJM
Service Type
—
Point of Interconnection
Toulon 138kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- N ILLINOIS HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AH2-340