PJM-AH2-341
140 MW storage in Stark, IL · In queue since March 2022 · Proposed COD July 2027
140 MW
Capacity
1
Components
Battery
4y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2027
Total Duration
5y 4m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-07-30
PJM-AH2-341 is a proposed 140 MW battery storage project located in Stark County, Illinois. The project, which consists entirely of battery storage, is interconnected within the ComEd service area and participates in the PJM Interconnection queue.
The project entered the PJM queue on March 10, 2022, with a proposed commercial operation date of July 30, 2027. Its interconnection agreement status is currently listed as "In Progress (unknown study)".
Generated from interconnection queue and public data sources
State
IL
County
Stark
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
ComEd
Entity
PJM
Service Type
—
Point of Interconnection
Toulon 138 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- N ILLINOIS HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.