PJM-AH2-344
45 MW hybrid in Marion, OH · In queue since March 2022 · Proposed COD March 2025
45 MW
Capacity
1
Components
Solar
4y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Total Duration
3 years
Schedule
14 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-03-07
PJM-AH2-344 is a proposed 45 MW hybrid solar and battery project located in Marion County, Ohio. The project, which consists of 45 MW of solar generation, is in the PJM interconnection queue as of March 10, 2022, with a proposed commercial operation date of March 7, 2025. The interconnecting utility is AEP, and the point of interconnection is the La Rue 138 kV substation.
The interconnection agreement status is listed as "In Progress (unknown study)".
Generated from interconnection queue and public data sources
State
OH
County
Marion
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
La Rue 138 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AH2-344