PJM-AH2-347
200 MW storage in St. Joseph, IN · In queue since March 2022 · Proposed COD March 2025
200 MW
Capacity
1
Components
Battery
4y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Total Duration
3 years
Schedule
14 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-03-07
PJM-AH2-347 is a proposed 200 MW battery storage project located in St. Joseph County, Indiana. The project, which consists entirely of battery storage, entered the PJM interconnection queue on March 10, 2022, with a proposed commercial operation date of March 7, 2025. The interconnecting utility is AEP.
The interconnection agreement (IA) status for the project is listed as "In Progress (unknown study)". The point of interconnection (POI) is the Northern St. Joseph 138 kV substation.
Generated from interconnection queue and public data sources
State
IN
County
St. Joseph
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
Northern St. Joseph 138 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AH2-347