Project PJM-AH2-347 — Project Summary

Queue ID
PJM-AH2-347
Capacity
200 MW
Technology
Battery
Status
active
Location
St. Joseph, IN
Region
PJM
Developer
IA Status
In Progress (unknown study)

PJM-AH2-347

PJM-AH2-347BetaActiveBatteryPJMLBNL + Live

200 MW storage in St. Joseph, IN · In queue since March 2022 · Proposed COD March 2025

200 MW

Capacity

1

Components

Battery

4y 2m

In Queue

In Progress (unknown study)

IA Status

COD target: 2025

Interconnection

Total Duration

3 years

Schedule

14 months past proposed COD

In Study38%
Queue EntryMar 10, 2022

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-03-07

About

PJM-AH2-347 is a proposed 200 MW battery storage project located in St. Joseph County, Indiana. The project, which consists entirely of battery storage, entered the PJM interconnection queue on March 10, 2022, with a proposed commercial operation date of March 7, 2025. The interconnecting utility is AEP.

The interconnection agreement (IA) status for the project is listed as "In Progress (unknown study)". The point of interconnection (POI) is the Northern St. Joseph 138 kV substation.

Generated from interconnection queue and public data sources

Project Details

State

IN

County

St. Joseph

Grid Region

PJM Interconnection

Market

ISO/RTO Member

Developer

Utility

AEP

Entity

PJM

Service Type

Point of Interconnection

Northern St. Joseph 138 kV

Data Source

LBNL + Live

Market Context
Approximate
ISO / RTO
PJM
Trading Hub
AEP-DAYTON HUB
Hub Confidence
MEDIUM

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Project PJM-AH2-347