PJM-AH2-351
1,000 MW generation in KY · In queue since March 2022 · Proposed COD December 2027
1,000 MW
Capacity
1
Components
Solar
4y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2027
Total Duration
5y 9m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-12-31
The proposed project PJM-AH2-351 is a 1000 MW solar generation project located in Kentucky, within the PJM Interconnection region. The project, which entered the queue on March 10, 2022, is being developed within the AEP utility territory. Its proposed commercial operation date is December 31, 2027.
The project's interconnection status is listed as "In Progress (unknown study)". The point of interconnection is the Jefferson - Hanging Rock 765 kV line. The project has appeared in recent news.
Generated from interconnection queue and public data sources
State
KY
County
—
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
Jefferson - Hanging Rock 765 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- CORNU 18 KV 1GT1
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.