PJM-AH2-352
400 MW generation in IN · In queue since March 2022 · Proposed COD December 2026
400 MW
Capacity
1
Components
Solar
4y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Total Duration
4y 9m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-12-31
PJM-AH2-352 is a proposed 400 MW solar generation project located in Indiana. The project, which interconnects to the Fall Creek 345 kV point of interconnection, was entered into the PJM interconnection queue on March 10, 2022. The developer is unknown. The proposed commercial operation date is December 31, 2026, and the interconnection agreement status is listed as "In Progress (unknown study)".
The project is located within the AEP utility service territory. It is currently listed as an active project in the PJM interconnection queue.
Generated from interconnection queue and public data sources
State
IN
County
—
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
Fall Creek 345 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- HIGH
- POI Substation
- Fall Creek Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.