PJM-AH2-353
1,000 MW generation in KY · In queue since March 2022 · Proposed COD December 2028
1,000 MW
Capacity
1
Components
Solar
4y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2028
Total Duration
6y 9m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-12-31
PJM-AH2-353 is a proposed solar generation project located in Kentucky, with a total capacity of 1000 MW. The project is interconnected within the PJM Interconnection queue, having entered the queue on March 10, 2022. The proposed commercial operation date is December 31, 2028. The interconnecting utility is AEP.
The interconnection agreement (IA) status for the project is listed as "In Progress (unknown study)". The point of interconnection (POI) is the Jefferson - Hanging Rock 765 kV line.
Generated from interconnection queue and public data sources
State
KY
County
—
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
Jefferson - Hanging Rock 765 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- CORNU 18 KV 1GT1
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.