PJM-AH2-363
200 MW hybrid in Kankakee, IL · In queue since March 2022 · Proposed COD March 2027
200 MW
Capacity
1
Components
Solar
4y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2027
Total Duration
5 years
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-03-31
PJM-AH2-363 is a proposed 200 MW hybrid solar and battery project located in Kankakee County, Illinois. The project, which consists of 200 MW of solar power, is in the PJM interconnection queue as of March 10, 2022, with a proposed commercial operation date of March 31, 2027. The interconnecting utility is ComEd, and the point of interconnection is the Davis Creek - Bloom 345 kV substation.
The project's interconnection status is listed as "In Progress (unknown study)". It is currently classified as an active project within the PJM queue. The developer is not specified in the available data, nor is there any indication of recent news coverage.
Generated from interconnection queue and public data sources
State
IL
County
Kankakee
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
ComEd
Entity
PJM
Service Type
—
Point of Interconnection
Davis Creek - Bloom 345 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- N ILLINOIS HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AH2-363