PJM-AH2-372
52 MW storage in Stephenson, IL · In queue since March 2022 · Proposed COD October 2028
52 MW
Capacity
1
Components
Battery
4y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2028
Total Duration
6y 7m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-10-01
PJM-AH2-372 is a proposed 52 MW battery storage project located in Stephenson County, Illinois. The project is interconnected within the PJM Interconnection queue, having entered the queue on March 10, 2022. The proposed commercial operation date is October 1, 2028.
The interconnection agreement for the project is currently listed as "In Progress (unknown study)". The project is located within the ComEd utility territory and connects to the grid at the Corbin _x0013_ Cresent Ridge 138kV point of interconnection.
Generated from interconnection queue and public data sources
State
IL
County
Stephenson
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
ComEd
Entity
PJM
Service Type
—
Point of Interconnection
Corbin _x0013_ Cresent Ridge 138kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- N ILLINOIS HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AH2-372