PJM-AH2-397
200 MW generation in Somerset, PA · In queue since March 2022 · Proposed COD October 2026
200 MW
Capacity
1
Components
Solar
4y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Total Duration
4y 7m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-10-01
PJM-AH2-397 is a proposed solar generation project with a total capacity of 200 MW, located in Somerset County, Pennsylvania. The project is interconnected within the PJM Interconnection queue, with an initial queue entry date of March 10, 2022. The proposed commercial operation date is October 1, 2026. The interconnection agreement status is currently listed as "In Progress (unknown study)".
The proposed project is located within the PENELEC utility territory. The point of interconnection is the Somerset 115 kV substation. Recent news coverage indicates public interest in the development of solar energy projects in the region.
Generated from interconnection queue and public data sources
State
PA
County
Somerset
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
PENELEC
Entity
PJM
Service Type
—
Point of Interconnection
Somerset 115 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- NBRIDGST69 KV T3
- POI Substation
- Somerset Substation