PJM-AH2-404
35 MW hybrid in Pittsylvania, VA · In queue since March 2022 · Proposed COD December 2026
35 MW
Capacity
1
Components
Solar
4y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Total Duration
4y 9m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-12-31
PJM-AH2-404 is a proposed 35 MW hybrid solar and battery energy storage project located in Pittsylvania County, Virginia. The project, which consists of 35 MW of solar capacity, is interconnected within the PJM Interconnection queue. Its point of interconnection is the East Danville - Banister 138kV substation.
The project entered the queue on March 10, 2022, with a proposed commercial operation date of December 31, 2026. The interconnection agreement (IA) status is currently listed as "In Progress (unknown study)". The interconnecting utility is AEP.
Generated from interconnection queue and public data sources
State
VA
County
Pittsylvania
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
East Danville - Banister 138kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AH2-404