PJM-AH2-405
100 MW generation in Franklin, PA · In queue since March 2022 · Proposed COD December 2026
100 MW
Capacity
1
Components
Solar
4y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Total Duration
4y 9m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-12-01
PJM-AH2-405 is a proposed solar generation project located in Franklin County, Pennsylvania, within the PJM Interconnection region. The project, with a total capacity of 100 MW, consists entirely of solar photovoltaic technology. It is currently listed as an active project in the PJM interconnection queue, with an entry date of March 11, 2022, and a proposed commercial operation date of December 1, 2026.
The interconnection service agreement status is listed as "In Progress (unknown study)". The designated point of interconnection (POI) is the McConnellsburg-Guilford 138 kV line. The utility associated with the project is APS.
Generated from interconnection queue and public data sources
State
PA
County
Franklin
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
APS
Entity
PJM
Service Type
—
Point of Interconnection
McConnellsburg-Guilford 138 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.