PJM-AH2-408
49.9 MW hybrid in Wood, OH · In queue since March 2022 · Proposed COD June 2025
49.9 MW
Capacity
1
Components
Solar
4y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Total Duration
3y 3m
Schedule
11 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-06-01
PJM-AH2-408 is a proposed 49.9 MW hybrid solar and battery project located in Wood County, Ohio. The project, which consists of 49.9 MW of solar capacity, is in the PJM interconnection queue as of March 10, 2022, with a proposed commercial operation date of June 1, 2025. The interconnecting utility is ATSI.
The project's interconnection agreement status is listed as "In Progress (unknown study)". The point of interconnection is the Fostoria - Lemoyne 138 kV line. The project is currently listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
State
OH
County
Wood
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
ATSI
Entity
PJM
Service Type
—
Point of Interconnection
Fostoria - Lemoyne 138 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AH2-408