PJM-AH2-409
30.1 MW hybrid in Wood, OH · In queue since March 2022 · Proposed COD June 2025
30.1 MW
Capacity
1
Components
Solar
4y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Total Duration
3y 3m
Schedule
11 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-06-01
The proposed project PJM-AH2-409 is a 30.1 MW hybrid solar and battery energy storage development project located in Wood County, Ohio. The project is interconnected to the ATSI utility network within the PJM Interconnection region. It consists of 30.1 MW of solar generation capacity.
The project entered the PJM interconnection queue on March 11, 2022, with a proposed commercial operation date of June 1, 2025. The interconnection agreement (IA) status is currently listed as "In Progress (unknown study)".
Generated from interconnection queue and public data sources
State
OH
County
Wood
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
ATSI
Entity
PJM
Service Type
—
Point of Interconnection
Fostoria - Lemoyne 138 kV II
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM