PJM-AH2-410
20 MW hybrid in KY · In queue since March 2022 · Proposed COD June 2025
20 MW
Capacity
1
Components
Solar
4y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Total Duration
3y 3m
Schedule
11 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-06-01
The proposed project PJM-AH2-410 is a 20 MW solar and battery hybrid project located in Kentucky within the PJM Interconnection region. The project, which consists of 20 MW of solar generation, is being developed within the East Kentucky Power Cooperative (EKPC) service area.
The project entered the PJM interconnection queue on March 10, 2022, with a proposed commercial operation date of June 1, 2025. Its interconnection agreement status is listed as "In Progress (unknown study)". The point of interconnection is the New Castle 69 kV substation.
Generated from interconnection queue and public data sources
State
KY
County
—
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
EKPC
Entity
PJM
Service Type
—
Point of Interconnection
New Castle 69 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- HIGH
- POI Substation
- New Castle Substation