PJM-AH2-412
7.35 MW generation in Cumberland, NJ · In queue since March 2022 · Proposed COD December 2022
7.35 MW
Capacity
1
Components
Solar
4y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2022
Total Duration
9 months
Schedule
41 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2022-12-31
The proposed project PJM-AH2-412 is a 7.35 MW solar generation project located in Cumberland County, New Jersey. The project is in the PJM interconnection queue as of March 10, 2022, with a proposed commercial operation date of December 31, 2022. The interconnection agreement status is listed as "In Progress (unknown study)".
The project is being developed within the Atlantic Electric Company (AEC) service territory. The point of interconnection is designated as "TBD 69kV". The project has appeared in recent news coverage regarding renewable energy development in the region.
Generated from interconnection queue and public data sources
State
NJ
County
Cumberland
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEC
Entity
PJM
Service Type
—
Point of Interconnection
TBD 69kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AH2-412