PJM-AH2-418
100 MW hybrid in Berrien, MI · In queue since March 2022 · Proposed COD December 2026
100 MW
Capacity
1
Components
Solar
4y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Total Duration
4y 9m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-12-31
PJM-AH2-418 is a proposed 100 MW hybrid solar and battery project located in Berrien County, Michigan. The project, which consists of 100 MW of solar generation, is in the PJM interconnection queue as of March 10, 2022, with a proposed commercial operation date of December 31, 2026. The interconnecting utility is AEP, and the point of interconnection is the Riverside - Pokagon 138 kV line.
The interconnection agreement status is listed as "In Progress (unknown study)".
Generated from interconnection queue and public data sources
State
MI
County
Berrien
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
Riverside - Pokagon 138 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AH2-418