PJM-AI1-009
100 MW hybrid in Rush, IN · In queue since April 2022 · Proposed COD December 2026
100 MW
Capacity
1
Components
Solar
4y 1m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Total Duration
4y 8m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-12-31
PJM-AI1-009 is a proposed 100 MW hybrid solar and battery project located in Rush County, Indiana. The project, which consists of 100 MW of solar capacity, is in the PJM interconnection queue as of April 1, 2022, with a proposed commercial operation date of December 31, 2026. The interconnection point is at the Pendleton - Tanners Creek 138 kV substation.
The project's interconnection agreement status is listed as "In Progress (unknown study)". The interconnecting utility is AEP.
Generated from interconnection queue and public data sources
State
IN
County
Rush
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
Pendleton - Tanners Creek 138 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- TANNERSC18 KV TC3
- POI Substation
- Tanners Creek