PJM-AI1-012
18.4 MW storage in Cumberland, VA · In queue since April 2022 · Proposed COD December 2026
18.4 MW
Capacity
1
Components
Battery
4y 1m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Total Duration
4y 8m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-12-31
PJM-AI1-012 is a proposed battery storage project with a total capacity of 18.4 MW. The project is located in Cumberland County, Virginia, and is being developed within the Dominion service area. It consists of a single 18.4 MW battery component.
The project is currently active in the PJM interconnection queue, having entered the queue on April 1, 2022, with a proposed commercial operation date of December 31, 2026. The interconnection agreement status is listed as "In Progress (unknown study)". The point of interconnection is the Buckingham- Farmville 230kV line.
Generated from interconnection queue and public data sources
State
VA
County
Cumberland
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
Dominion
Entity
PJM
Service Type
—
Point of Interconnection
Buckingham- Farmville 230kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AI1-012