PJM-AI1-013
200 MW storage in Charles City, VA · In queue since April 2022 · Proposed COD December 2026
200 MW
Capacity
1
Components
Battery
4y 1m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Total Duration
4y 8m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-12-31
PJM-AI1-013 is a proposed 200 MW battery storage project located in Charles City County, Virginia. The project is in the PJM interconnection queue as of April 1, 2022, with a proposed commercial operation date of December 31, 2026. Dominion is the listed utility.
The interconnection agreement for the project is currently listed as "In Progress (unknown study)". The point of interconnection is the Chickahominy 230 kV substation.
Generated from interconnection queue and public data sources
State
VA
County
Charles City
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
Dominion
Entity
PJM
Service Type
—
Point of Interconnection
Chickahominy 230 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- CHICKHOM34.5 KV CHICK2SP
- POI Substation
- Chickahominy Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.