1.98 MW generation in — · In queue since April 2022 · Proposed COD March 2023
1.98 MW
Capacity
1
Components
Solar
4y 1m
In Queue
In Progress (unknown study)
IA Status
COD target: 2023
Total Duration
11 months
Schedule
38 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-03-31
The proposed project PJM-AI1-020 is a 1.98 MW solar generation project located within the PJM Interconnection region. The project, with Delmarva Power & Light (DPL) as the utility, entered the PJM queue on April 2, 2022, and has a proposed commercial operation date of March 31, 2023.
The interconnection agreement (IA) status for the project is listed as "In Progress (unknown study)".
Generated from interconnection queue and public data sources
State
—
County
—
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
DPL
Entity
PJM
Service Type
—
Point of Interconnection
TBD
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Hub Confidence