PJM-AI1-038
95.76 MW generation in Carbon, PA · In queue since April 2022 · Proposed COD March 2024
95.76 MW
Capacity
1
Components
Solar
4y 1m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Total Duration
1y 11m
Schedule
25 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-03-31
PJM-AI1-038 is a proposed solar generation project with a total capacity of 95.76 MW. The project is located in Carbon County, Pennsylvania, within the PJM Interconnection region, and is in the interconnection queue of PJM. The queue entry date is April 12, 2022, with a proposed commercial operation date of March 31, 2024. The interconnecting utility is PPL.
The interconnection agreement status is listed as "In Progress (unknown study)".
Generated from interconnection queue and public data sources
State
PA
County
Carbon
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
PPL
Entity
PJM
Service Type
—
Point of Interconnection
Harwood-Siegfried 230kV II
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AI1-038