PJM-AI1-039
200 MW hybrid in Clearfield, PA · In queue since April 2022 · Proposed COD June 2025
200 MW
Capacity
1
Components
Solar
4y 1m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Total Duration
3y 2m
Schedule
10 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-06-30
PJM-AI1-039 is a proposed 200 MW solar and battery hybrid project located in Clearfield County, Pennsylvania. The project consists of 200 MW of solar generation paired with battery storage. It is interconnected within the PJM Interconnection queue as of April 19, 2022, with a proposed commercial operation date of June 30, 2025.
The project's interconnection agreement status is listed as "In Progress (unknown study)". The point of interconnection is the Moshannon-Milesburg 230 kV VIII line, and the interconnecting utility is PENELEC. The project is currently listed as active within the PJM queue.
Generated from interconnection queue and public data sources
State
PA
County
Clearfield
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
PENELEC
Entity
PJM
Service Type
—
Point of Interconnection
Moshannon-Milesburg 230 kV VIII
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.