PJM-AI1-053
6.6 MW hybrid in Mercer, PA · In queue since June 2022 · Proposed COD December 2022
6.6 MW
Capacity
1
Components
Solar
3y 11m
In Queue
In Progress (unknown study)
IA Status
COD target: 2022
Total Duration
6 months
Schedule
42 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2022-12-01
PJM-AI1-053 is a proposed hybrid energy project located in Mercer County, Pennsylvania, within the PJM Interconnection region. The project, with a total capacity of 6.6 MW, consists of a 6.6 MW solar component and also includes a diesel component. The project entered the PJM interconnection queue on June 10, 2022, with a proposed commercial operation date of December 1, 2022. The interconnection agreement status is currently listed as "In Progress (unknown study)" with utility ATSI.
The proposed project is interconnected at the McDowell - Campbell 69 kV point of interconnection. The project is listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
State
PA
County
Mercer
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
ATSI
Entity
PJM
Service Type
—
Point of Interconnection
McDowell - Campbell 69 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- HIGH
- POI Substation
- J H Campbell
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AI1-053