PJM-AI1-074
120 MW hybrid in Jackson, OH · In queue since July 2022 · Proposed COD December 2027
120 MW
Capacity
1
Components
Solar
3y 10m
In Queue
In Progress (unknown study)
IA Status
COD target: 2027
Total Duration
5y 5m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-12-15
PJM-AI1-074 is a proposed 120 MW hybrid solar and battery project located in Jackson County, Ohio. The project, which consists of 120 MW of solar capacity, is in the PJM interconnection queue as of July 5, 2022, with a proposed commercial operation date of December 15, 2027. The interconnecting utility is AEP, and the point of interconnection is the Corwin - Elk 138 kV line.
The interconnection agreement for PJM-AI1-074 is currently in progress, with the study status unknown.
Generated from interconnection queue and public data sources
State
OH
County
Jackson
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
Corwin - Elk 138 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AI1-074