PJM-AI1-076
19.8 MW generation in Delaware, PA · In queue since July 2022 · Proposed COD June 2024
19.8 MW
Capacity
1
Components
Solar
3y 10m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Total Duration
1y 11m
Schedule
22 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-06-30
PJM-AI1-076 is a proposed solar generation project with a total capacity of 19.8 MW. The project is located in Delaware County, Pennsylvania, within the PJM Interconnection region and is in the PECO utility territory. The project entered the PJM queue on July 11, 2022, with a proposed commercial operation date of June 30, 2024.
The interconnection agreement status for PJM-AI1-076 is listed as "In Progress (unknown study)". The point of interconnection is TBD at 13.2 kV. The project is currently listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
State
PA
County
Delaware
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
PECO
Entity
PJM
Service Type
—
Point of Interconnection
TBD 13.2 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.