PJM-AI1-082
15 MW generation in Westmoreland, PA · In queue since July 2022 · Proposed COD December 2026
15 MW
Capacity
1
Components
Solar
3y 10m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Total Duration
4y 5m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-12-01
PJM-AI1-082 is a proposed solar generation project located in Westmoreland County, Pennsylvania. The project, with a total capacity of 15 MW, is in the PJM interconnection queue as of July 28, 2022, and has a proposed commercial operation date of December 1, 2026. The interconnection agreement is currently listed as "In Progress (unknown study)".
The project is being developed within the Allegheny Power Systems (APS) service area. The point of interconnection (POI) is the Laurel 25 kV substation. The project has appeared in recent news coverage regarding renewable energy development in the PJM region.
Generated from interconnection queue and public data sources
State
PA
County
Westmoreland
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
APS
Entity
PJM
Service Type
—
Point of Interconnection
Laurel 25 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- LAURELDP69 KV LOADT1
- POI Substation
- Laurel Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.