PJM-AI1-100
150 MW hybrid in Belmont, OH · In queue since August 2022 · Proposed COD December 2025
150 MW
Capacity
1
Components
Solar
3y 9m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Total Duration
3y 4m
Schedule
4 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-12-31
PJM-AI1-100 is a proposed 150 MW hybrid solar and battery project located in Belmont County, Ohio. The project consists of 150 MW of solar generation. It is listed in the PJM interconnection queue as of August 30, 2022, with a proposed commercial operation date of December 31, 2025. The interconnection point is at the Somerton - Norton 138 kV substation. The interconnection agreement status is listed as "In Progress (unknown study)".
The project is in the PJM queue under queue ID PJM-AI1-100. The interconnecting utility is AEP.
Generated from interconnection queue and public data sources
State
OH
County
Belmont
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
Somerton - Norton 138 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AI1-100