PJM-AI1-106
9.9 MW hybrid in Halifax, VA · In queue since August 2022 · Proposed COD December 2023
9.9 MW
Capacity
1
Components
Solar
3y 9m
In Queue
In Progress (unknown study)
IA Status
COD target: 2023
Total Duration
1y 4m
Schedule
28 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-12-31
PJM-AI1-106 is a proposed 9.9 MW hybrid solar and battery project located in Halifax County, Virginia. The project, which consists of 9.9 MW of solar capacity, is interconnected within the PJM Interconnection queue. Its queue entry date is August 31, 2022, with a proposed commercial operation date of December 31, 2023. The interconnection agreement (IA) status is currently listed as "In Progress (unknown study)".
The project is being developed within Dominion's service territory. The point of interconnection (POI) is the Sinai 13.2 kV substation. The project is listed as active in the PJM queue.
Generated from interconnection queue and public data sources
State
VA
County
Halifax
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
Dominion
Entity
PJM
Service Type
—
Point of Interconnection
Sinai 13.2 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AI1-106