PJM-AI1-109
1,310 MW generation in Middlesex, NJ · In queue since September 2022 · Proposed COD December 2029
1,310 MW
Capacity
1
Components
Offshore Wind
3y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2029
Total Duration
7y 3m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-12-31
PJM-AI1-109 is a proposed offshore wind generation project located in Middlesex County, New Jersey, within the PJM Interconnection region. The development project, with a total capacity of 1310 MW, is being proposed by PSEG. It entered the PJM queue on September 1, 2022, with a proposed commercial operation date of December 31, 2029. The interconnection agreement (IA) status is currently listed as "In Progress (unknown study)".
The project consists entirely of offshore wind generation, totaling 1310 MW. The point of interconnection (POI) is the Deans 500 kV substation. The project is currently listed as active within the PJM interconnection queue.
Generated from interconnection queue and public data sources
State
NJ
County
Middlesex
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
PSEG
Entity
PJM
Service Type
—
Point of Interconnection
Deans 500 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- BRUNSWIC26 KV MIDDL2SP
- POI Substation
- Deans Switching Station
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AI1-109