1,310 MW generation in Monmouth, NJ · In queue since September 2022 · Proposed COD December 2029
1,310 MW
Capacity
1
Components
Offshore Wind
3y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2029
Total Duration
7y 3m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-12-31
PJM-AI1-110 is a proposed offshore wind generation project located in Monmouth County, New Jersey, with a total capacity of 1310 MW. The project, which consists entirely of offshore wind turbines, is interconnected to the Jersey Central Power & Light (JCPL) system at the Larrabee 230 kV V point of interconnection.
The project is currently active in the PJM interconnection queue, having entered the queue on September 1, 2022, with a proposed commercial operation date of December 31, 2029. The interconnection agreement (IA) status is listed as "In Progress" with an unknown study. The developer is not specified in the queue data.
Generated from interconnection queue and public data sources
State
NJ
County
Monmouth
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
JCPL
Entity
PJM
Service Type
—
Point of Interconnection
Larrabee 230 kV V
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- LARRABEE230 KV FRENCHSP
- POI Substation
- Larrabee Substation