PJM-AI1-114
9.9 MW hybrid in Cambria, PA · In queue since September 2022 · Proposed COD December 2025
9.9 MW
Capacity
1
Components
Solar
3y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Total Duration
3y 3m
Schedule
4 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-12-31
PJM-AI1-114 is a proposed 9.9 MW hybrid solar and battery project located in Cambria County, Pennsylvania. The project, consisting of 9.9 MW of solar generation, is in the PJM interconnection queue as of September 2, 2022, with a proposed commercial operation date of December 31, 2025. The interconnecting utility is PENELEC, and the point of interconnection is the Revloc 46 kV substation.
The project's interconnection agreement status is listed as "In Progress (unknown study)".
Generated from interconnection queue and public data sources
State
PA
County
Cambria
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
PENELEC
Entity
PJM
Service Type
—
Point of Interconnection
Revloc 46 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- EBENSBUR13 KV NUG GE
- POI Substation
- Revloc Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AI1-114