PJM-AI1-118
37.6 MW generation in Warren, NJ · In queue since September 2022 · Proposed COD September 2025
37.6 MW
Capacity
1
Components
Solar
3y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Total Duration
3 years
Schedule
7 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-09-29
PJM-AI1-118 is a proposed solar generation project with a total capacity of 37.6 MW, located in Warren County, New Jersey. The project is interconnected to the JCPL utility network and is in the PJM interconnection queue as of September 6, 2022. The proposed commercial operation date is September 29, 2025.
The interconnection agreement for PJM-AI1-118 is currently listed as "In Progress (unknown study)". The point of interconnection is the Pequest river - Gilbert 115 kV location.
Generated from interconnection queue and public data sources
State
NJ
County
Warren
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
JCPL
Entity
PJM
Service Type
—
Point of Interconnection
Pequest river - Gilbert 115 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- 955 RIVE16 KV RV-2
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.