PJM-AI1-119
28.8 MW generation in Kendall, IL · In queue since September 2022 · Proposed COD June 2026
28.8 MW
Capacity
1
Components
Solar
3y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Total Duration
3y 9m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-06-30
PJM-AI1-119 is a proposed solar generation project located in Kendall County, Illinois, within the PJM Interconnection region. The project, with a total capacity of 28.8 MW, consists entirely of solar photovoltaic generation. Its interconnection queue entry date is September 6, 2022, with a proposed commercial operation date of June 30, 2026. The project is currently active in the PJM queue, with its interconnection agreement status listed as "In Progress (unknown study)". The interconnecting utility is ComEd, and the point of interconnection is the Shorewood 138kV substation.
Generated from interconnection queue and public data sources
State
IL
County
Kendall
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
ComEd
Entity
PJM
Service Type
—
Point of Interconnection
Shorewood 138kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- N ILLINOIS HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AI1-119