PJM-AI1-126
10 MW generation in Cumberland, VA · In queue since September 2022 · Proposed COD September 2024
10 MW
Capacity
1
Components
Solar
3y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Total Duration
2 years
Schedule
19 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-09-30
PJM-AI1-126 is a proposed 10 MW solar generation project located in Cumberland County, Virginia. The project is in the PJM interconnection queue as of September 8, 2022, with a proposed commercial operation date of September 30, 2024. Dominion is the interconnecting utility.
The interconnection agreement for the project is currently listed as "In Progress (unknown study)". The point of interconnection is the Farmville 12.47kV grid location.
Generated from interconnection queue and public data sources
State
VA
County
Cumberland
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
Dominion
Entity
PJM
Service Type
—
Point of Interconnection
Farmville 12.47kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- FARMVILL13 KV TX1
- POI Substation
- Farmville Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.