PJM-AI1-130
75 MW storage in Baltimore, MD · In queue since September 2022 · Proposed COD September 2026
75 MW
Capacity
1
Components
Battery
3y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Total Duration
4 years
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-09-07
PJM-AI1-130 is a proposed 75 MW battery storage project located in Baltimore County, Maryland. The project, interconnecting to Baltimore Gas & Electric (BGE) at the Northeast-CP Crane 115kV point of interconnection, entered the PJM interconnection queue on September 9, 2022, with a proposed commercial operation date of September 7, 2026. Its interconnection agreement status is currently listed as "In Progress (unknown study)".
The development project consists solely of battery storage, with a total capacity of 75 MW. The project is currently listed as active within the PJM queue.
Generated from interconnection queue and public data sources
State
MD
County
Baltimore
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
BGE
Entity
PJM
Service Type
—
Point of Interconnection
Northeast-CP Crane 115kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AI1-130