PJM-AI1-132
83 MW hybrid in Washington, KY · In queue since September 2022 · Proposed COD April 2029
83 MW
Capacity
1
Components
Solar
3y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2029
Total Duration
6y 7m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-04-30
PJM-AI1-132 is a proposed 83 MW hybrid solar and battery project located in Washington County, Kentucky. The project, which consists of 83 MW of solar generation, is in the PJM interconnection queue as of September 8, 2022, with a proposed commercial operation date of April 30, 2029. The interconnecting utility is EKPC.
The project's interconnection agreement status is listed as "In Progress (unknown study)". The point of interconnection is the Fredricksburg 69 kV substation. The developer is not specified in the queue data.
Generated from interconnection queue and public data sources
State
KY
County
Washington
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
EKPC
Entity
PJM
Service Type
—
Point of Interconnection
Fredricksburg 69 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.